Dependency Mapping
What are Dependencies?
Definition: Work that relies on other work to complete.
Simple Example
Task A: Design API
Task B: Implement API client
Dependency: B depends on A (can't implement client until API is designed)
Why Dependencies Matter
- Block work: If A is delayed, B is blocked
- Cascade delays: One delay affects multiple tasks
- Coordination needed: Teams must sync
- Risk: Dependencies are points of failure
Why Dependency Mapping Matters
1. Identify Risks (Blocked Work)
Without Mapping:
"Why isn't the mobile app done?" → "Waiting for API from backend team" (surprise!)
With Mapping:
Dependencies identified upfront → Coordinate with backend team → No surprises
2. Sequence Work Properly
Bad Sequence:
Week 1: Start mobile app
Week 2: Realize we need API first
Week 3: Wait for API
Week 4: Resume mobile app (wasted 2 weeks)
Good Sequence:
Week 1-2: API design and implementation
Week 3-4: Mobile app (no waiting)
3. Plan Capacity Realistically
Without Dependencies:
"We can do 3 projects in parallel!" (all blocked on same dependency)
With Dependencies:
"Project A must finish before B and C can start" (realistic plan)
4. Coordinate Cross-Team Work
Example:
Mobile team depends on:
• Backend team (API)
• Platform team (Push notifications)
• Design team (UI mockups)
→ Need coordination meetings, shared timeline
Types of Dependencies
1. Finish-to-Start (Most Common)
Definition: B starts after A finishes
Example:
A: Design API ──finish──> B: Implement client
Real-world:
- API must be designed before client can be implemented
- Database schema must be created before migrations run
- Design must be approved before development starts
2. Start-to-Start
Definition: B starts when A starts
Example:
A: Backend development ──start together──> B: Frontend development
Real-world:
- Backend and frontend can start together (using API contract)
- Testing can start when development starts (test-driven development)
3. Finish-to-Finish
Definition: B finishes when A finishes
Example:
A: Feature development ──finish together──> B: Documentation
Real-world:
- Documentation finishes when feature finishes
- Testing finishes when development finishes
4. External Dependencies
Definition: Depends on vendor, partner, or outside team
Example:
Our work: Payment integration
External dependency: Stripe API availability
Real-world:
- Third-party API availability
- Vendor deliverables
- Legal/compliance approvals
- Partner integrations
Dependency Identification
1. Technical Dependencies (Shared Libraries, APIs)
Questions:
- What shared code do we depend on?
- What APIs do we call?
- What libraries do we use?
Example:
Mobile app depends on:
• Auth library (shared)
• User API (backend team)
• Analytics SDK (platform team)
2. Data Dependencies (Schema Changes)
Questions:
- What database tables do we use?
- What schema changes are needed?
- Who else uses this data?
Example:
New feature: User profiles
Data dependencies:
• Add `bio` column to `users` table (DBA approval needed)
• Migrate existing users (data team)
• Update analytics queries (analytics team)
3. Team Dependencies (Need Another Team's Work)
Questions:
- What work from other teams do we need?
- When do we need it?
- What happens if it's delayed?
Example:
Mobile app launch depends on:
• Backend team: API endpoints (week 4)
• Platform team: Push notification service (week 8)
• Design team: UI mockups (week 2)
• QA team: Testing (week 10)
4. Resource Dependencies (Shared Resources)
Questions:
- What shared resources do we need?
- Who else needs them?
- Can we parallelize?
Example:
Both projects need:
• Senior engineer (can't work on both simultaneously)
• Staging environment (can't deploy both at once)
• Database migration window (only one migration at a time)
5. Knowledge Dependencies (Need Expertise)
Questions:
- What expertise do we need?
- Who has it?
- Can they be available?
Example:
Blockchain integration depends on:
• Crypto expert (only 1 person on team)
• Security review (external consultant)
• Legal review (compliance team)
Dependency Mapping Techniques
1. Dependency Matrix (Grid of Projects)
Format:
│ Proj A │ Proj B │ Proj C │ Proj D
─────────┼────────┼────────┼────────┼────────
Proj A │ - │ X │ │
Proj B │ │ - │ X │ X
Proj C │ │ │ - │
Proj D │ │ │ X │ -
X = Depends on (row depends on column)
Reading:
- Proj A depends on Proj B
- Proj B depends on Proj C and Proj D
- Proj D depends on Proj C
Pros:
- Shows all dependencies at once
- Easy to spot circular dependencies
Cons:
- Hard to read with many projects
- Doesn't show timing
2. Network Diagram (Nodes and Edges)
Format:
[API Design] ──> [Mobile App] ──> [Beta Launch]
│ │
└──> [Web App] ┘
Pros:
- Visual and intuitive
- Shows flow of work
- Easy to identify critical path
Cons:
- Can get messy with many dependencies
3. Gantt Chart with Dependency Lines
Format:
Task │ Week 1 │ Week 2 │ Week 3 │ Week 4
─────────────┼────────┼────────┼────────┼────────
API Design │████████│ │ │
Mobile App │ │████████│████████│
Web App │ │████████│████████│
Beta Launch │ │ │ │████████
│ │ ↑ │ │ ↑
│ │ └────────────────┘
│ │ (dependency)
Pros:
- Shows timeline
- Shows dependencies and sequence
Cons:
- Implies specific dates (may be too rigid)
4. Story Mapping with Dependencies
Format:
Epic: Mobile App Launch
User Story 1: API Design ──┐
User Story 2: UI Design │
User Story 3: Mobile Dev ──┘ (depends on 1 and 2)
User Story 4: Testing ─────┘ (depends on 3)
User Story 5: Launch ──────┘ (depends on 4)
Pros:
- Connects to agile workflow
- Shows user value
Cons:
- Less visual than network diagram
Visualizing Dependencies
Color Coding by Type
Colors:
- 🔴 Red: Critical dependency (blocks multiple tasks)
- 🟡 Yellow: Important dependency (blocks one task)
- 🟢 Green: Nice-to-have dependency (doesn't block)
- 🔵 Blue: External dependency (outside our control)
Example:
[API Design] ──🔴──> [Mobile App] (critical: blocks mobile and web)
[UI Design] ──🟡──> [Mobile App] (important: blocks mobile only)
[Analytics] ──🟢──> [Mobile App] (nice-to-have: doesn't block launch)
[Stripe API] ──🔵──> [Payment] (external: vendor dependency)
Arrows Showing Direction
Convention:
A ──> B (B depends on A)
A <── B (A depends on B)
A <──> B (mutual dependency, circular!)
Critical Path Highlighting
Critical Path: Longest chain of dependencies (determines minimum project duration)
Example:
Path 1: API (2w) → Mobile (4w) → Testing (1w) = 7 weeks
Path 2: UI (1w) → Mobile (4w) → Testing (1w) = 6 weeks
Path 3: Analytics (2w) = 2 weeks
Critical Path: Path 1 (7 weeks) ← Optimize this!
Highlight:
[API Design] ══> [Mobile App] ══> [Testing] ══> [Launch]
2w 4w 1w (7w total)
══ = Critical path (bold/highlighted)
Dependency Strength (Hard vs Soft)
Hard Dependency: Must have, blocks work Soft Dependency: Nice to have, doesn't block
Example:
[API] ═══> [Mobile App] (hard: can't build without API)
[Analytics] ···> [Mobile App] (soft: can launch without analytics)
═══ = Hard dependency (solid line)
··· = Soft dependency (dotted line)
Critical Path Analysis
What is Critical Path?
Definition: Longest chain of dependencies that determines minimum project duration.
Why It Matters:
- Determines earliest completion date
- Shows where to focus optimization
- Identifies highest-risk dependencies
Finding Critical Path
Steps:
- List all tasks and durations
- Map dependencies
- Calculate all possible paths
- Identify longest path
Example:
Tasks:
A: API Design (2 weeks)
B: UI Design (1 week)
C: Mobile Dev (4 weeks, depends on A and B)
D: Testing (1 week, depends on C)
E: Analytics (2 weeks, independent)
Paths:
Path 1: A (2w) → C (4w) → D (1w) = 7 weeks ← Critical path!
Path 2: B (1w) → C (4w) → D (1w) = 6 weeks
Path 3: E (2w) = 2 weeks
Critical Path: A → C → D (7 weeks)
Optimizing Critical Path
Strategies:
- Reduce task duration: Make critical tasks faster
- Parallelize: Do tasks concurrently
- Remove dependencies: Break coupling
- Add resources: More people on critical tasks
Example:
Before:
A (2w) → C (4w) → D (1w) = 7 weeks
After optimization:
• Reduce A from 2w to 1w (use API contract, start C early)
• Parallelize D with C (test while developing)
A (1w) → C (4w) = 5 weeks (2 weeks saved!)
→ D (concurrent)
Managing Dependencies
1. Make Dependencies Explicit (Document)
Dependency Register:
| Dependency | Type | Owner | Needed By | Status | Risk |
|------------|------|-------|-----------|--------|------|
| API endpoints | Technical | Backend team | Week 4 | In progress | Medium |
| UI mockups | Team | Design team | Week 2 | Done | Low |
| Push service | Platform | Platform team | Week 8 | Not started | High |
2. Prioritize Breaking Dependencies (Reduce Coupling)
Strategies:
- Use API contracts (agree interface, implement independently)
- Feature flags (deploy independently, enable together)
- Mocks/stubs (develop against fake dependencies)
Example:
Before:
Mobile app waits for API to be fully implemented (4 weeks blocked)
After:
1. Define API contract (1 day)
2. Mobile team builds against mock API (no waiting)
3. Backend team implements real API (parallel work)
4. Integration testing (1 week)
Result: 3 weeks saved
3. Coordinate with Dependent Teams
Coordination Mechanisms:
- Shared roadmap (visibility)
- Weekly sync meetings (alignment)
- Slack channel (quick questions)
- Written agreements (SLAs, contracts)
Example:
Mobile team + Backend team coordination:
• Shared roadmap: Both teams see API deadline (week 4)
• Weekly sync: Monday 10am, review progress
• Slack: #mobile-backend-integration
• Agreement: API contract signed, backend commits to week 4 delivery
4. Have Contingency Plans
Risk Mitigation:
- Plan B if dependency is delayed
- Workarounds
- Fallback options
Example:
Dependency: Push notification service (week 8)
Risk: Platform team may delay
Contingency plans:
• Plan B: Use third-party service (Firebase)
• Workaround: Launch without push, add later
• Fallback: Email notifications instead
Reducing Dependencies
1. API Contracts (Agree Interface, Implement Independently)
Process:
- Define API contract (input, output, errors)
- Both teams agree on contract
- Teams implement independently
- Integration testing
Example:
# API Contract
POST /api/users
Request:
{
"email": "user@example.com",
"name": "John Doe"
}
Response:
{
"id": "123",
"email": "user@example.com",
"name": "John Doe",
"created_at": "2024-01-15T10:00:00Z"
}
Errors:
400: Invalid email
409: Email already exists
Benefits:
- Teams work in parallel
- No waiting
- Clear expectations
2. Feature Flags (Deploy Independently, Enable Together)
Process:
- Backend deploys API (feature flag off)
- Frontend deploys client (feature flag off)
- Both teams test independently
- Enable feature flags together
Example:
// Backend
if (featureFlags.isEnabled('new-api')) {
return newAPI(req);
} else {
return oldAPI(req);
}
// Frontend
if (featureFlags.isEnabled('new-api')) {
callNewAPI();
} else {
callOldAPI();
}
Benefits:
- Deploy anytime
- No coordination needed for deployment
- Can rollback independently
3. Mocks/Stubs (Develop Against Fake Dependencies)
Process:
- Create mock service (fake API)
- Develop against mock
- Swap mock for real service later
Example:
// Mock API for development
const mockAPI = {
getUser: (id) => ({
id,
name: 'Mock User',
email: 'mock@example.com'
})
};
// Real API for production
const realAPI = {
getUser: (id) => fetch(`/api/users/${id}`)
};
// Use mock in development, real in production
const api = process.env.NODE_ENV === 'development' ? mockAPI : realAPI;
Benefits:
- No waiting for real API
- Faster development
- Can test edge cases
4. Modular Architecture (Loose Coupling)
Principles:
- Each module has clear interface
- Modules don't depend on internals of other modules
- Changes in one module don't affect others
Example:
Before (Tight Coupling):
Mobile app directly queries backend database (high dependency)
After (Loose Coupling):
Mobile app calls API → API queries database (low dependency)
Benefits:
- Easier to change
- Easier to test
- Easier to parallelize work
Dependency Risks
1. Blocked Work (Upstream Not Delivered)
Risk:
Mobile app ready to start (week 3)
API not delivered until week 6
Result: Mobile team blocked for 3 weeks
Mitigation:
- Identify dependencies early
- Use mocks to unblock
- Have contingency plans
2. Cascading Delays (One Delay Affects Many)
Risk:
API delayed by 2 weeks
→ Mobile app delayed by 2 weeks
→ Web app delayed by 2 weeks
→ Beta launch delayed by 2 weeks
Mitigation:
- Reduce dependencies (break coupling)
- Parallelize work where possible
- Buffer time in schedule
3. Integration Issues (Parts Don't Fit Together)
Risk:
Backend implements API one way
Frontend expects API another way
Result: Integration fails, rework needed
Mitigation:
- API contracts (agree upfront)
- Integration testing (test early)
- Regular syncs (catch issues early)
Dependency Tracking
Dependency Register
Template:
# Dependency Register
| ID | Dependency | Type | Owner | Dependent | Needed By | Status | Risk | Notes |
|----|------------|------|-------|-----------|-----------|--------|------|-------|
| D1 | API endpoints | Technical | Backend | Mobile | Week 4 | In progress | Medium | On track |
| D2 | UI mockups | Team | Design | Mobile | Week 2 | Done | Low | Completed |
| D3 | Push service | Platform | Platform | Mobile | Week 8 | Not started | High | Risk of delay |
| D4 | Stripe API | External | Stripe | Payment | Week 6 | Blocked | High | Waiting for approval |
Status Tracking
Statuses:
- Not Started: Dependency work hasn't begun
- In Progress: Dependency work is ongoing
- Blocked: Dependency is blocked by something else
- At Risk: Dependency may be delayed
- Done: Dependency is complete
- Resolved: Dependency is no longer needed
Regular Check-Ins
Weekly Dependency Review:
- Review dependency register
- Update statuses
- Identify new dependencies
- Escalate blocked dependencies
- Adjust plans if needed
Example Agenda:
Weekly Dependency Review (Mondays, 10am)
1. Review each dependency (5 min each)
- Status update
- Any blockers?
- On track for deadline?
2. New dependencies (10 min)
- Any new dependencies identified?
- Add to register
3. Escalations (10 min)
- Which dependencies are at risk?
- Who can help unblock?
4. Action items (5 min)
- What needs to happen this week?
Cross-Team Coordination
1. Shared Roadmaps
Purpose: All teams see each other's plans
Example:
Q1 2024 Roadmap (All Teams)
Backend Team:
• API v2 (weeks 1-4)
• Database migration (weeks 5-8)
Mobile Team:
• Mobile app (weeks 3-10, depends on API v2)
Platform Team:
• Push notifications (weeks 1-8)
• Analytics (weeks 9-12)
Dependencies:
• Mobile depends on Backend (API v2, week 4)
• Mobile depends on Platform (Push, week 8)
2. Integration Meetings
Purpose: Coordinate work across teams
Frequency: Weekly or bi-weekly
Agenda:
Integration Meeting (Wednesdays, 2pm)
1. Progress updates (10 min)
- Each team shares progress
- Highlight any delays
2. Dependency review (15 min)
- Review dependency register
- Update statuses
- Identify blockers
3. Integration planning (15 min)
- When will integration happen?
- Who will do integration testing?
- What's the rollback plan?
4. Action items (5 min)
3. Slack Channels for Coordination
Purpose: Quick questions and updates
Example:
#mobile-backend-integration
• Quick questions about API
• Status updates
• Blocker notifications
#platform-integrations
• All teams integrating with platform
• Announcements (new services, breaking changes)
4. Written Contracts/Agreements
Purpose: Clear expectations and commitments
Example:
# API Integration Agreement
**Backend Team Commits:**
- Deliver API v2 by week 4 (Feb 1)
- API will support 1000 req/s
- 99.9% uptime SLA
- Breaking changes communicated 2 weeks in advance
**Mobile Team Commits:**
- Provide API requirements by week 1 (Jan 8)
- Test against staging API (week 3)
- Report bugs within 24 hours
**Escalation:**
- If API delayed: Escalate to Engineering Manager
- If bugs not fixed: Escalate to Product Manager
Dependency Anti-Patterns
1. Hidden Dependencies (Not Documented)
Problem:
Week 8: "Why isn't the mobile app done?"
Team: "We're waiting for the push notification service"
Manager: "I didn't know about that dependency!"
Solution: Document all dependencies upfront
2. Circular Dependencies (A → B → A)
Problem:
A depends on B
B depends on C
C depends on A
→ Deadlock! Nothing can start.
Solution: Break the cycle (redesign to remove circular dependency)
3. Too Many Dependencies (Tight Coupling)
Problem:
Mobile app depends on:
• 5 backend APIs
• 3 platform services
• 2 external vendors
• 4 shared libraries
→ High risk of being blocked
Solution: Reduce dependencies (use mocks, break coupling)
4. Ignored Dependencies (Surprise at Integration Time)
Problem:
Week 10: Integration time
"The API returns XML, but we expected JSON!"
→ Rework needed, 2 weeks delay
Solution: API contracts, integration testing early
Tools
Jira (Issue Linking)
Features:
- Link issues (blocks, is blocked by)
- Dependency visualization
- Roadmap view with dependencies
Example:
MOBILE-123: Mobile app
Blocked by: BACKEND-456 (API v2)
Blocked by: PLATFORM-789 (Push service)
Monday.com (Dependency Columns)
Features:
- Dependency columns
- Gantt chart with dependencies
- Automation (notify when dependency is done)
Microsoft Project (Gantt)
Features:
- Gantt chart with dependency lines
- Critical path analysis
- Resource leveling
Miro (Visual Mapping)
Features:
- Visual dependency mapping
- Collaborative
- Flexible (can create any format)
Real Dependency Mapping Examples
Example 1: Mobile App Launch
Dependency Map:
[API Design] ──> [API Implementation] ──> [Mobile App] ──> [Beta Launch]
2w 4w 6w 1w
[UI Design] ──> [Mobile App]
1w 6w
[Push Service] ──> [Mobile App]
8w 6w
Critical Path: API Design → API Implementation → Mobile App → Beta Launch (13 weeks)
Risks:
• Push Service (8w) may not be ready when Mobile App needs it (week 6)
• Mitigation: Start Push Service earlier, or launch without push initially
Example 2: Platform Migration
Dependency Matrix:
│ DB Migration │ API v2 │ Mobile │ Web │ Analytics
──────────────┼──────────────┼────────┼────────┼─────┼──────────
DB Migration │ - │ X │ │ │
API v2 │ │ - │ X │ X │
Mobile │ │ │ - │ │
Web │ │ │ │ - │
Analytics │ X │ X │ │ │ -
Dependencies:
• API v2 depends on DB Migration
• Mobile depends on API v2
• Web depends on API v2
• Analytics depends on DB Migration and API v2
Critical Path: DB Migration → API v2 → Mobile (longest chain)
Templates
Template 1: Dependency Matrix
# Dependency Matrix
| | Proj A | Proj B | Proj C | Proj D |
|----------|--------|--------|--------|--------|
| Proj A | - | | | |
| Proj B | X | - | | |
| Proj C | | X | - | |
| Proj D | | X | X | - |
X = Row depends on Column
Template 2: Network Diagram
# Dependency Network
[Task A] ──> [Task B] ──> [Task D] │ │ └──> [Task C]┘
Critical Path: A → B → D
Template 3: Dependency Register
# Dependency Register
| ID | Dependency | Type | Owner | Dependent | Needed By | Status | Risk | Mitigation |
|----|------------|------|-------|-----------|-----------|--------|------|------------|
| D1 | [Name] | [Technical/Team/External] | [Team] | [Project] | [Date] | [Status] | [High/Med/Low] | [Plan] |
Summary
Quick Reference
Dependency Types:
- Finish-to-Start: B starts after A finishes (most common)
- Start-to-Start: B starts when A starts
- Finish-to-Finish: B finishes when A finishes
- External: Vendor, partner, outside team
Mapping Techniques:
- Dependency matrix (grid)
- Network diagram (nodes and edges)
- Gantt chart (timeline with dependencies)
- Story mapping (agile-friendly)
Critical Path:
- Longest chain of dependencies
- Determines minimum duration
- Focus optimization here
Managing Dependencies:
- Make explicit (document)
- Prioritize breaking (reduce coupling)
- Coordinate with teams (meetings, Slack)
- Have contingency plans (Plan B)
Reducing Dependencies:
- API contracts (agree interface)
- Feature flags (deploy independently)
- Mocks/stubs (fake dependencies)
- Modular architecture (loose coupling)
Risks:
- Blocked work
- Cascading delays
- Integration issues
Tools:
- Jira (issue linking)
- Monday.com (dependency columns)
- Microsoft Project (Gantt)
- Miro (visual mapping)
Anti-Patterns:
- Hidden dependencies
- Circular dependencies
- Too many dependencies
- Ignored dependencies
Examples
Read the usage examples in the source repository.
View source ↗Source history
- Indexed on
- 2026-01-20
- Index updated
- 2026-01-26
- Branch
- main
Index and sync dates describe this directory. View the source repository for code history.
GitHub ↗chat Comments (0)
Sign in to join the discussion and leave a comment.
No comments yet. Be the first to share your thoughts!